Started with forwarding the right ports to our internal devices (ACP on NUC and Web Power Switch).
Now, where we had good polar alignment and balance we wanted to try what happens if the scope is fully extended upwards and the roof opens:
The rubber on the roof slightly touched the scope - which we were OK with. But there was a wooden bar behind the rubber that passed the scope by barely 1"!
... lots of deliberation...
... and we finally decided to have the pier shortened by 6".
Michael knew a guy who has a full welding and metal shop. He could pickup the scope in the afternoon and have it ready the next day.
So, we disassembled everything :-( and loaded the scope on Rory's truck...
... and with that, we had a quiet evening.